Sitterson Hall · 2022–2024

Making room for
undergraduate CS.

Access.
Collaboration.
Belonging.

The design of the
CS Experience Labs

The Co-Lab in fall 2023. Shared monitors, adjustable workstations, round tables, and a communal counter in Sitterson 155 and 156.

From the first brief ↓

The brief

A good place to work should be a shared resource.

A large monitor. A comfortable chair. Space to work beside someone who can help. These are ordinary tools for learning computer science. In 2022, they were far from ordinary for all of our students.

The CS Experience Labs began with a question about access: what could we make available together that students could not all provide for themselves?

The answer grew from a small lab into a coworking space, learning labs, group rooms, and a lounge. This is the story of the physical design—and of the student use that kept changing it.

2022

Establish the need

Survey equipment access, develop the pitch, and begin the room swap.

2023

Test, revise, open

Learn from a working prototype. Install the Co-Lab in August.

2024

Extend down the hall

Bring the learning and group rooms into the same shared environment.

01 / Access as a design problem

Start with the students’ working conditions.

In the September 2022 survey, access to a second monitor differed sharply across the displayed gender groups. The October funding pitch connected that gap to a broader problem: students lacked a shared place to work and belong.

By late September, the existing undergraduate lab had eight workstations with second monitors. Students could gather, but equipped places to work were scarce.

The early App Lab with mismatched desks, chairs and monitors on a raised tile floor.
The App Lab in summer 2022, before the move upstairs. Photograph preserved in the two-year report.

Work and learning in the App Lab.

In September 2022, the XL was already a place to work and gather. Students brought laptops to desks with shared monitors, worked alongside one another, and came together for presentations. The renovation would give those activities more room and better equipment.

Students seated at desks facing two presenters, with monitors and floor lamps along the App Lab walls
8 September 2022Students gathered for a presentation in the App Lab.
Students with laptops and shared monitors at reused desks, beneath floor lamps in the App Lab
20 September 2022Students at work in the App Lab.

Bring your laptop.
Use a better workspace.

Large external monitors, ergonomic seating, and adjustable surfaces would make the equipment useful across students’ own computers.

Make help easier
to give and receive.

Office hours needed room for a student and a learning assistant to see the same screen, write together, and move between conversations.

Make room
for informal work.

Not every exchange belongs at a workstation. Round tables and lounge seating would give students other ways to work together.

02 / The first spatial vision

Move the people into the people room.

The first step was a swap: move machines toward the former machine room and give students Sitterson 156, alongside 155. The October 2022 proposal imagined a coworking hub next to a flexible learning lab.

I used SketchUp to work through how desks, monitors, collaboration tables, and a welcome point might fit. Those models were a way to test the brief, and a starting point for the design work with Melissa Cutter Jordan and UNC Design.

Sitterson 156 before renovation, with computer racks, stored equipment and crowded worktables
22 September 2022The room we were starting with.Old computer racks, towers, boxes, and crowded worktables filled Sitterson 156.
A child tries a white VR headset among the old lab tables and computer racks, with an adult at the right edge
5 October 2022Try the future room in VR.A VR preview in the existing lab, while the physical space still held its old equipment.
October 2022 oblique SketchUp view of proposed workstation rows, shared tables and the learning lab behind glass.

A room with several ways to work.

The early model set a direction: concentrated work along shared benches, conversation at round tables, and a learning room visible through the glass. Furniture, quantities, finishes, and circulation would all continue to change.

November 2022
→ January 2023

Use the room before the design is finished.

After the November walkthrough, we fast-tracked carpet and paint and put existing furniture to work. By January, the prototype was in regular use. Watching partners roll their chairs together made bench-leg placement a practical design question.

An emptied lab with exposed floor sections and finish samples on the walls
27 December 2022Clear the room.The room was cleared during renovation; flooring and furniture work were still ahead.
The furnished interim lab with a navy wall, reused red chairs, sofas and perimeter workstations
2 February 2023Put the prototype to work.Paint, carpet, reused lounge seating, and workstations made an interim room. The new phase-one furniture would arrive in August.

Turn the brief into a plan.

While the prototype was in use, the drawings made the design more specific: where finishes would change, how the two rooms connected, and which arrangements could fit.

Finish plan locating navy accent walls and listing the paint, carpet and base finishes
19 December 2022Set the finish direction.The December notes specify Anchors Aweigh navy accents, Pure White walls, and Analog Mono Equivalent carpet.Plan issued through Melissa Cutter Jordan / UNC Facilities Planning and Design.
Proposed furniture plan for rooms 155 and 156, showing shared benches, rounds and project tables
16 February 2023Work through the layout.The February proposal places benching, round collaboration tables, and perimeter workstations in SN156 beside the smaller SN155 learning room.Plan issued through Melissa Cutter Jordan / UNC Facilities Planning and Design.

04 / August 2023

The Co-Lab opens.

Furniture installation began on August 24. By the end of the month, students were using the new space, and the August 31 announcement shared the result.

The room offered individual workstations, tables for small groups, and a counter at the edge. The learning lab could change between office hours and workshops.

The original launch flyover of phase one: ergonomic seats, monitor arms, standing desks, and 27-inch monitors that charge laptops over USB-C. The film is silent; its original labels remain visible.

A milestone, then follow-through

Opening did not end the design work. Glassboard replacement and leveling continued into November. Later feedback brought further changes to writing space, chair arms, and cable management.

05 / The student hallway, 2024

One shared home.
Different kinds of rooms.

The second phase extended the work along Sitterson’s first-floor south corridor. Learning labs, team rooms, smaller rooms, and a lounge supported different scales of conversation.

As costs and scope were reviewed, usable rooms, furniture, paint, and carpet took priority over larger architectural changes. The main furniture order was approved on January 29, 2024; installation activity followed in March.

Revisit the learning-lab setup.

The second phase had its own revisions. Across six months, the SN136 study changed from seated-height tables for paired work to standing-height project tables with shared screens and writing surfaces.

July SN136 rendering with two groups of seated-height tables and rolling chairs
26 July 2023Start at seated height.The July concept uses paired worktables and Setu chairs.Alfred Williams & Company validation packet, coordinated through Melissa Cutter Jordan / UNC Facilities Planning and Design.
January SN136 rendering with standing project tables, fabric dividers, writing panels and monitor arms
24 January 2024Move toward project tables.The January study adds standing-height surfaces, fabric screens, screen-mounted boards, and monitor arms.Alfred Williams & Company validation packet, coordinated through Melissa Cutter Jordan / UNC Facilities Planning and Design.
Phase-two seating sheet with armless Setu chairs and a stool crossed out with the words Removed from scope
24 January 2024Revise the seating, too.The January sheet specifies armless Setu chairs and explicitly marks one stool option as removed from scope.Alfred Williams & Company validation packet, coordinated through Melissa Cutter Jordan / UNC Facilities Planning and Design.

Keep the alternatives visible.

The annotation matters: a product can remain on a working sheet after it has been dropped. Here the revision records both the armless chair direction and the stool that did not continue.

Circulation

Keep the benches shallower.

A 30-inch-deep alternative tightened the space behind occupied chairs. With frequent turnover during office hours, we retained 24-inch surfaces to protect circulation.

Writing space

Support several conversations.

I proposed distributing horizontal boards across multiple walls. Melissa and Alan checked positions, door clearances, and the realities of installation. The plan continued to evolve in March.

Privacy

Consider the view from the door.

In the shallow focus room, SN146, I proposed reversing the desk and board so a user’s work did not face the hallway. Melissa checked the door swing and egress before revising the arrangement.

Resolve the rooms together.

The March drawing places learning rooms, team rooms, compact workspaces, and writing surfaces along one corridor. Room-by-room decisions had to work as a whole.

Architectural plan of the Sitterson hallway with furniture layouts and writing-surface dimensions across rooms 135 through 147 and the existing Co-Lab
5 March 2024The hallway furniture planDesk orientation, table heights, board sizes, and door clearances appear together in the plan. The drawing’s title block dates it March 5, 2024.Plan issued through Melissa Cutter Jordan / UNC Facilities Planning and Design. Title block: MJ.
A second-phase room with two rows of white desks, monitors, monitor arms and ergonomic chairs
28 March 2024Equipment reaches the rooms.Desks, monitors, arms, and chairs in a second-phase room during the March installation period.

From the drawing to the daily setup.

The drawing coordinates a program across many rooms. The photograph brings the scale back to one workstation: a place for a laptop, an external display, and enough room to sit and work.

Sitterson 135 before its renovation: an empty room with a bookcase, old floor finishes and blank walls.
Sitterson 135, beforeAn existing room waiting for a new use.
The same Sitterson 135 room after renovation, equipped for group study.
Sitterson 135, afterA table, display, and boards turn the room into a shared working space.

April 2024

The later report records phase two as completed in April. On April 23, the contemporary update still noted the sectional and summer touch-up painting as outstanding. The broad milestone and remaining items belong together.

06 / Carpet selection

Finding the floor.

The carpet had to work with the furniture, the light, and the rooms already around it.

Two rounds of selection shaped different parts of the XL: the original rooms in 2022, then the hallway expansion in 2023–2024.

Historical simulation of dark carpet in the unrenovated room, with equipment racks and a bookcase still in place
Shared 5 December 2022Phase one / Analog Mono in EquivalentAn archived J&J room-visualizer study for the original lab. The later physical samples paired carpet with the proposed paint colors.

December 2022 · Rooms 155 & 156

A backdrop for the first rooms.

Melissa brought samples, I talked them over with students, and we tried J&J’s room visualizer. We chose Analog Mono in Equivalent over Correlate, whose lighter, higher-contrast pattern felt washed out in the preview.

Equivalent gave us a backdrop for bright walls, white furniture, and color from the chairs.

Pale-blue Eames chair standing on a dark carpet sample
Shared 4 December 2023Test it with the furniture.Melissa’s photograph places a pale-blue chair on a physical sample. The sample’s exact carpet color is not established.

December 2023 · The hallway expansion

Compare it in a familiar setting.

I asked Melissa to place the new samples beside the Eames tables and blue chairs. Digital previews provided another comparison: five Bentley options placed into a photograph of the main Co-Lab.

The Co-Lab was keeping its existing carpet. Its furniture and light gave us a familiar setting for choosing the hallway’s floor.

One room.
Five alternatives.

These comparisons were shared on December 19, 2023. The first image is the existing room; the other five are archived carpet simulations for the hallway selection.

Photograph of the existing Co-Lab with white tables, blue chairs, and its original dark patterned carpet

Existing room photograph

The familiar reference

The main Co-Lab kept its existing carpet. This photograph was the reference for comparing colors for the hallway expansion.

Historical Bentley simulation showing Multiplay II Clans carpet in the Co-Lab reference room

Historical carpet simulation

Multiplay II / Clans

Selected for the XL hallway and adjoining rooms. Its subtle blue connected the carpet to the room finishes.

Historical Bentley simulation showing Multiplay II Cooldown carpet in the Co-Lab reference room

Historical carpet simulation

Multiplay II / Cooldown

Selected for the surrounding corridors, where it worked with the existing palette.

Historical Bentley simulation showing Multiplay II Easter Eggs carpet in the Co-Lab reference room

Historical carpet simulation

Multiplay II / Easter Eggs

One of the alternatives compared during selection. This was a digital study, not an installed floor.

Historical Bentley simulation showing Shapeshifter II Alter carpet in the Co-Lab reference room

Historical carpet simulation

Shapeshifter II / Alter

The comparison also included the Shapeshifter II family, with a different arrangement of lines and color.

Historical Bentley simulation showing Shapeshifter II Changelings carpet in the Co-Lab reference room

Historical carpet simulation

Shapeshifter II / Changelings

A second Shapeshifter II option. The final hallway selections came from the Multiplay II family.

Historical comparisons made with Bentley’s room visualizer. Clans was selected for the XL hallway and adjoining rooms; Cooldown for the surrounding corridors.

From the sample
to the installation.

Color was only part of the choice. Melissa developed the layout, and I approved the plan on February 9. The XL area went down first; the surrounding corridors followed in March.

Cropped carpet installation plan showing red tile patterns in the XL hallway and surrounding corridors, while rooms 155 and 156 remain unpatterned
Drawing 5 February · Approved 9 February 2024Plan the direction, too.The installation plan distinguishes the hallway and adjoining rooms from the retained floors in 155 and 156. Tile direction was part of the decision: I wanted the lines to draw people into the rooms.Plan developed through Melissa Cutter Jordan / UNC Facilities Planning and Design.
New carpet being installed along the XL hallway, with materials and unfinished work visible
12 February 2024The XL hallway takes shape.The XL-area carpet was installed February 12–13. The photograph records the work in progress, alongside the navy trim and blue accent wall.
Dark linear carpet running down a long corridor with unfinished wall base
16 March 2024The surrounding corridors follow.The lines run along the long hallway. Wall base and transitions still needed attention at this stage.
Meeting room with dark patterned carpet, a light table, gray chairs, and whiteboards on a blue accent wall
31 March 2024A floor beneath the shared work.A meeting-room photograph shows the installed carpet with a shared table, gray chairs, and writing surfaces on a blue accent wall.

08 / Resourcing the work

The budget changed
as the scope became real.

A proposal, a working budget, an order, and a later funding summary answer different questions.

These amounts mark decisions in the record. They should not be read as one continuous series of project spending.

4 October 2022

$200,000
Funding request

The education and technology funding proposal requested workstations and renovation. This was the requested investment, not an approval or a final cost.

15 November 2022

$120–130k
Working design budget

The post-walkthrough next steps recorded this approximate envelope. Fast-tracking carpet and paint would allow use of the room while furniture design and lead times continued.

3–4 May 2023

$80,200.61
Revised furniture quote · design approved

The revised vendor quote included its design and installation services. I approved the design on May 4. This furniture scope was only part of the phase-one project.

29 January 2024

Under $125k
Phase-two furniture + whiteboard estimate

Melissa reported this scope, including Capisco seating, when requesting approval for the main furniture order. I approved moving ahead; whiteboards remained subject to a check of construction and painting actuals.

November 2024
Retrospective report

$165k
Phase one
$185k
Phase two

The two-year report describes renovation and furniture funding of $165,000 for phase one, completed August 2023, and $185,000 for phase two, completed April 2024.

The final pair are reported funding amounts, not audited actual spending. The report discusses monitor funding separately. The January estimate covers a narrower furniture and whiteboard scope.

A university space, made together

The design continued
after the doors opened.

The most useful feedback came from people using the rooms.

A request from learning assistants for another writing surface. A chair that needed to move more easily. A cable that made a shared station harder to use. Each was a chance to bring the space closer to the original purpose: helping more students do good work together.

Kris Jordan

Mission and equity rationale; student-use evidence; early spatial models and SketchUp alternatives; product research and trials; functional requirements; design selections and approvals.

Melissa Cutter Jordan · UNC Design

Spatial and finish design; alternatives and product suggestions; site and clearance checks; samples, specifications, vendor coordination, and implementation follow-through.

A wider collaboration

Powell Marshall supported funding and project coordination. Alan Moran coordinated construction and field work. Andrea Janusz contributed architectural scope and shops coordination. Elizabeth Wallace and Alfred Williams & Company’s designers developed specifications and validation documents. The furniture packet renderings shown here were coordinated through Melissa and UNC Facilities Planning and Design; individual rendering authors are not established.

UNC Facilities, Tar Heel Painters, Creative Business Interiors, and installation teams carried the work into the building. Students and learning assistants helped test how the rooms should work.

Roles are drawn from the design correspondence and the two-year report; the contributions and approvals are credited separately.

About the record

This retrospective draws on the project’s dated slide decks, saved design studies, room photographs, and selected correspondence from 2022–2024. The narrative is paraphrased; private correspondence is not reproduced here.

  1. CSXL Funding Priority, October 2022: the equipment-access argument, early room models, and proposed program. Proposed furniture counts are not treated as installed counts.
  2. Kris Jordan’s February 12, 2023 SketchUp images; March finish decisions; April table-size tests; and the May 4 design approval.
  3. XL Fall 2023 and XL Launch: authentic phase-one flyovers. The opening hero uses an excerpt of the first film.
  4. Hallway design and installation correspondence, 2023–2024, including the January 29 order approval and April 23 status update.
  5. UNC Facilities Planning and Design plans dated December 19, 2022, February 16, 2023, and March 5, 2024; Alfred Williams & Company validation packets from February–May 2023, July 2023, and January 2024. The March hallway plan is dated by its title block; its original filename retains 2023.
  6. Project photographs dated August 2022–April 2024; the February 2, 2023 vinyl application film; June 2022 typography studies and the preserved CSXL identity vectors. Vector file modification dates are not treated as design or approval dates.
  7. Carpet selection correspondence and archived J&J and Bentley visualizations, December 2022 and December 2023; the February 5, 2024 carpet plan, February 9 approval, and February–March installation photographs. Dates on emailed samples and simulations indicate when they were shared.
  8. Selected 4,000-pixel room-sign artwork exported from Sitterson Room Signs. The artwork’s design and approval dates are not established; dated installed photographs are identified separately. The exported SN141 artwork reads “Big Team,” while the March 2024 photograph in the private record reads “Big Group.”
  9. App Lab photographs from September 8 and 20, 2022, showing presentations and shared work. Capture dates were checked against the original photographs; these views are distinct from the later renovated rooms.
  10. XL 2-year Report, November 2024, pp. 9 and 11–14: reported funding, completion milestones, and room photographs; p. 27: collaborators.

Survey chart percentages are approximate, and its displayed-group total differs from the deck’s overall sample. Later completion summaries do not imply every correction or addition was finished on opening day.